Show the Work Plan Critical Path
This article explains how to show the work plan critical path in the OnePlan Gantt.
Video Length - 1:22
To show the critical path in the work plan:
(Optional) Open the Gantt chart view by clicking on the Gantt icon in the work plan header.
Open the Grid Options menu, then select Gantt > Show Critical path. Work items on the critical path for your work plan will be highlighted in red in both the work plan grid and the Gantt chart.