Mapping Progress Between Microsoft Project Professional to OnePlan

This article explains OnePlan best practices for mapping progress fields between Project Professional and OnePlan.

This article specifically discusses the mappings for the fields % Done/% Complete and Actual/Timesheet Hours.

By default, this integration maps progress fields between OnePlan and Project Professional (i.e. % Done in OnePlan to % Complete in Project). It does not map Timesheet Hours (OnePlan) to Actual Hours (Project).

This is because the integration only supports mapping either % Complete or Actual Hours in Project Professional. Not both at the same time.

Important

If users want to map timesheet hours, our product recommendation is to map Timesheet Hours (OnePlan) to a custom field in Project Professional, in place of Actual Hours.

Alternatively, users can remove the % Complete field in Project, and add in the Actual Hours field. Then they can map Timesheet Hours (OnePlan) to Actual Hours (Project).